Sarasota Memorial Hospital has updated its schedule for concrete pouring this month at its North Port campus project.

Concrete pours will take place at 2 a.m. on the following dates (setup at 1 a.m.):

  • May 12
  • May 19
  • May 27

An additional pour will take place at 6 a.m. (setup at 5 a.m.) on the following date:

  • May 29

For overnight operations, traffic control will include:

  • Communication with the North Port Police Department detail team
  • A dedicated flagman on-site to manage movement and safety
  • Cement trucks staged on-site to minimize disruption
  • Dispatching trucks in controlled intervals (two at a time every 15-30 minutes)

The pours are necessary to maintain the project schedule, ensure proper concrete curing time and conditions in Florida’s climate and minimize traffic congestion and safety impacts along Sumter Boulevard during peak daytime hours.

The City Commission approved SMH’s request to conduct this work at its Jan. 13, 2026, meeting.

For more information from SMH, visit smh.com/northportupdatesResidents are encouraged to check the SMH North Port page weekly for updates, as the schedule is subject to change.