Road Rehabilitation Project

Road Rehab Project Banner.png

 

Road resurfacing program 

Every year, the City repairs and resurfaces roadways so they are safer, last longer and are less expensive to maintain. Roads are selected annually based on their condition and available funding. Please see the list below for current projects scheduled for 2023-24.

*Scheduled work dates are weather-sensitive and subject to change.

Major road projects for 2023-24

Toledo Blade Boulevard Road Rehabilitation Phase I

Toledo Phase I Map.jpg The first phase of Toledo Blade Blvd. rehabilitation will include the 3.6 miles of Toledo Blade Blvd. between N. Cranberry Blvd. and W. Price Blvd.

Roadwork on Toledo Blade Blvd. is currently scheduled to begin Wednesday, Jan. 3, 2024, with work estimated to be completed around mid-February. Work will take place overnight from 7 p.m. to 6 a.m. In the event you have to travel on Toledo Blade Blvd. during these hours, please allow extra time for travel and exercise caution when in the area.

Toledo Blade Boulevard Road Rehabilitation Phase II

The second phase of Toledo Blade Blvd. rehabilitation will include the 2.8 miles of Toledo Blade Blvd. between W. Price Blvd. and Bobcat Trail.

Scheduled work dates, a map and traffic plan of the area will be made available as soon as possible.

Lamarque Avenue

Lamarque-Phase-I-Map.jpg(PDF, 5MB) The Lamarque Ave. phase of the Road Rehabilitation Project has been completed.

Eldron Avenue

Eldron Phase I Map.jpg The Eldron Ave. phase of the Road Rehabilitation Project includes 1.05 miles of sub-division roadways as listed for Eldron Ave.

Beginning Thursday, Dec. 7, road paving crews will be returning to Eldron Ave. to finish repaving the roadway. Work is estimated to be completed on Wednesday, Dec. 13. Please allow for extra travel time and exercise caution when traveling in the area.

Ponce de Leon Boulevard over I-75 overpass

(PDF, 4MB)Ponce-Overpass-Map.jpg(PDF, 4MB) The Ponce de Leon Blvd. phase of road rehabilitation will include repaving the section of Ponce de Leon Blvd. that passes over I-75.  

Work on this area is scheduled to resume and be completed on Thursday, Dec. 14, and will occur during normal daytime hours, 7 a.m. to 5 p.m. with flaggers on site to help direct traffic in the work area. Please allow for extra travel time and exercise caution when traveling in the area.

S. Salford Boulevard

The Salford Blvd. phase of the Road Rehabilitation Project will include the 1.4 miles of S. Salford Blvd. between Lothair Ave. and Barbary Lane.

Scheduled work dates, a map and traffic plan of the area will be made available as soon as possible.

 

How do I get my road paved?

The City develops its resurfacing list based on citizen requests. These requests can be made through the North Report app. All road requests for resurfacing are evaluated for priority in our resurfacing program. As our resurfacing budget is established, candidate roads for resurfacing are submitted to the City Commission for approval. Due to limited funding, it may be several years before a road enters the program. In the meantime, we will patch it as necessary. New roads are added to this list every year and are re-prioritized each year.